Past Projects:

  • Lover’s Lane: Replaced 280’ of main line (April 2008)
  • Monte Vista Terrace: Replaced 200’ of main for County project (Jan 2008)
  • Hwy. 116 at Church St: Relocated water main for Cal Trans project (Jan 2008)
  • Center St., Villa Grande: Replaced 275’ of main line (Completed FY 2007-08)
  • Merry Lane: Replaced 300’ of main line (Completed FY 2007-08)
  • Orchard Lane: Replaced 120’ of main line (Completed FY 2007-08)
  • Western Ave.: Replaced 140’ of main line (Completed FY 2007-08)
  • Orchard Ave.: Replaced 120’ of main line (Completed FY 2006-07)
  • Old Cazadero Road: Replaced 275’ of main line (Completed FY 2006-07)
  • Replaced Crespo Tank (Completed November 2007)
  • Buttner Ave: Replaced 500’ main line (Completed July 2007)
  • Center Street: Relocated 275’ of main line (Completed July 2007)
  • Hwy. 116 east of Monte Rio (Completed FY 2006-07): Replaced 1,900’ of main line
  • Hwy. 116 at Foothill Blvd (Completed FY 2006-07): Replaced 250’ of main line
  • Guerne Way (Completed FY 2005-06): Replaced 400’ of main line
  • Beach Avenue (Completed FY 2004-05): Replaced 410’ of main line
  • Melody Avenue (Completed FY 2004-05): Replaced 900’ of main line
  • CIP Phase III-B (Completed July 2004)Installation of the Guerneville Treatment PlantInstallation of hypo chlorite generating systems at both Highland and Monte Rio Treatment plantsInstallation of a SCADA (Supervisory Control and Data Acquisition) systemReplacement of 6930’ of main line in Guerneville and 2150’ of main line in Monte RioReplacement/upgrade of tanks at Highland and Monte RosaBooster station improvements at Monte Rosa, Park Ave. And Summit Ave.
  • CIP Phase III-A (Completed October, 2003)Replacement of 7,000’ feet of main in Guerneville – including downtown Guerneville -- and 14,900’ of main in Monte RioAddition of 22 hydrants