SWSD header SWSD logo










Capital Improvements


Construction Projects (Last updated: 5/18/2010)

construction photo
construction photo
construction photo

Current Projects

Fiscal Year 2010 – started April 2010

  • Schoolhouse Tank and Upper Schoolhouse Tank: Construct a storage tank with a capacity of approximately 65,000 gallons at the top of Bonita Terrace; install a booster station and connect with replacement reservoir at Upper Schoolhouse site.
  • Bonita Terrace: Replace 1,500 ft of existing main and appurtences on Bonita Terrace, including ties to Schoolhouse Tank and Delta Way (improvements completed 2009), to create a loop.
  • Handy Andy booster Feed Line: Replace 300 lf of existing main between Hwy. 116 and the booster pump at Old Monte Rio Road.
  • Riverlands Road (GV): Replace 1,600 lf of existing main and appurtenances.
sws_image4

Fiscal Year 2011 – starting July 2010

  • Alder Road, Pebble Way, & Heller Street: On River Blvd., Alder Rd., Willow Rd., and Railroad Ave. – Replace existing mains and appurtenances with approximately 6,000 lf of 6-inch water main, to complete loop. Abandon 4,500 lf of parallel undersized water main and transfer water services to larger main.
tank replacement

Recently Completed Projects
(completed 2009)

  • Monte Vista and Mesa Grande Terrace: Replaced 4,500’ of main line and upgrade fire protection
  • Southeastern side of the Terraces: Replaced 3,900’ of main line and allow for fire protection
  • Riverside Drive: Replaced 1,600 lf of main
  • East Guernewood Road: Replaced 1,150 lf of existing main between Neeley Road and the Summer Crossing.
  • Camino del Arroyo: Replaced segment at creek crossing. Replaced pipe was old concrete-asbestos pipe that crossed the creek unprotected.
sws_image6

Past Projects:

  • Lover’s Lane: Replaced 280’ of main line (April 2008)
  • Monte Vista Terrace: Replaced 200’ of main for County project (Jan 2008)
  • Hwy. 116 at Church St: Relocated water main for Cal Trans project (Jan 2008)
  • Center St., Villa Grande: Replaced 275’ of main line (Completed FY 2007-08)
  • Merry Lane: Replaced 300’ of main line (Completed FY 2007-08)
  • Orchard Lane: Replaced 120’ of main line (Completed FY 2007-08)
  • Western Ave.: Replaced 140’ of main line (Completed FY 2007-08)
  • Orchard Ave.: Replaced 120’ of main line (Completed FY 2006-07)
  • Old Cazadero Road: Replaced 275’ of main line (Completed FY 2006-07)
  • Replaced Crespo Tank (Completed November 2007)
  • Buttner Ave: Replaced 500’ main line (Completed July 2007)
  • Center Street: Relocated 275’ of main line (Completed July 2007)
  • Hwy. 116 east of Monte Rio (Completed FY 2006-07): Replaced 1,900’ of main line
  • Hwy. 116 at Foothill Blvd (Completed FY 2006-07): Replaced 250’ of main line
  • Guerne Way (Completed FY 2005-06): Replaced 400’ of main line
  • Beach Avenue (Completed FY 2004-05): Replaced 410’ of main line
  • Melody Avenue (Completed FY 2004-05): Replaced 900’ of main line
  • CIP Phase III-B (Completed July 2004)
    • Installation of the Guerneville Treatment Plant
    • Installation of hypo chlorite generating systems at both Highland and Monte Rio Treatment plants
    • Installation of a SCADA (Supervisory Control and Data Acquisition) system
    • Replacement of 6930’ of main line in Guerneville and 2150’ of main line in Monte Rio
    • Replacement/upgrade of tanks at Highland and Monte Rosa
    • Booster station improvements at Monte Rosa, Park Ave. And Summit Ave.
  • CIP Phase III-A (Completed October, 2003)
    • Replacement of 7,000’ feet of main in Guerneville – including downtown Guerneville -- and 14,900’ of main in Monte Rio
    • Addition of 22 hydrants

sws_image8

sws_image9

sws_image10



Home
Email the District at: info@sweetwatersprings.com

Copyright © 2008 Sweetwater Springs. All rights reserved.